Project Progress: Applecross, WA

Jan 2020

Works are progressing well at Densford Civil's Applecross site where they are installing offline storage tanks in a 4.5 metre deep excavation. All of this 3 metres below the water table. The project has proven to be quite the challenge in such a highly sensitive area to manage the high level of dewatering required as well as the treatment of acid sulfate soils encountered on site.